1950 OLD GALLOWS ROAD, SUITE 750
VIENNA, VA 22182
PHONE: 703.506.1990   FAX: 703.506.1140
EMAIL: INFO@BRIGLIALAW.COM

slogan2.gif
BrigliaMcLaughlin, PLLC
SHANNON J. BRIGLIA TO PRESENT CLE ON TOP 15 VIRGINIA CONSTRUCTION LAW CASES THAT EVERY PRACTITIONER SHOULD KNOW. PDF Print

 

March 30, 2011 - BrigliaMcLaughlin is pleased to announce that Shannon J. Briglia will be presenting a live and interactive telephone seminar for Virginia CLE on May 17, 2011 from 12:00 p.m. to 2:00 p.m. titled The Top 15 Virginia Construction Law Cases That Every Practitioner Should Know.

Read more...
 
ROBERT J. DIETZ HAS BEEN MADE OF COUNSEL TO BRIGLIAMCLAUGHLIN. PDF Print

January 6, 2012 - BrigliaMcLaughlin, PLLC, a nationally recognized construction law firm based in Tysons Corner, Virginia, is pleased to announce that Robert J. Dietz has been made Of Counsel to the firm.

Mr. Dietz, a 2004 graduate of the Washington & Lee University School of Law, has been with the firm since December 2008. A transplanted Floridian, he earned his Bachelor of Arts from the University of Florida in 2000. Prior to joining the firm, Mr. Dietz served first as a judicial law clerk to the Honorable John H. Tisdale in the Circuit Court for Frederick County, Maryland.  Thereafter, he associated with other national and regional construction law firms, focusing his practice in the areas of construction law, government contracts and surety defense.  Since joining the firm, Mr. Dietz has continued to refine his areas of practice and hone his trial skills, obtaining numerous successful outcomes for our clients in a variety of matters in Virginia and Maryland courts. Mr. Dietz will continue expanding his experience and taking on added responsibility for the firm’s clients and management in his new role with the firm.

To read more about Robert J. Dietz, click here.

 
RECENT CHANGES TO VIRGINIA'S LITTLE MILLER ACT ALTER THE RULES FOR CERTAIN PARTIES TO FILE CLAIMS AGAINST PAYMENT BONDS. PDF Print

December 13, 2011 - On March 25, 2011, the Virginia legislature threw a curve ball to companies supplying labor or materials on public construction projects.  This curve ball makes it both easier and harder for second-tier claimants to satisfy the prerequisites to filing suit against a payment bond. 

Read more...
 
NORTH CAROLINA COURT RULES THAT “NO DAMAGES FOR DELAY” CLAUSE DOES NOT TRUMP “EQUITABLE ADJUSTMENT” CLAUSE FOR COST ESCALATION CLAIMS. PDF Print

January 25, 2012 - In Southern Seeding Serv., Inc. v. W.C. English, Inc., 2011 WL 6039951 (N.C. App. Dec. 6, 2011), the North Carolina Court of Appeals found that a "no damages for delay" clause does not trump an "equitable adjustment" clause in the same construction subcontract. While labor and material cost escalation are normally perceived as an element of delay damages, the court in this case found that a separate contract provision distinguishing these costs permitted their recovery.

In Southern Seeding, the defendant subcontracted to perform grading and grassing work for a project located in Greensboro, North Carolina, and in turn sub-subcontracted a portion of the seeding and grassing work to the plaintiff. The parties' agreement contained an "equitable adjustment" clause stating:

Unit prices herein quoted are based upon the assumption that the contract will be completed within time as specified in the specifications at time of bidding. Should our work be delayed beyond said time without fault on our part, unit prices herein quoted shall be equitably adjusted to compensate us for increased cost...."

A separate provision in the agreement contained a standard "no damages for delay" clause, prohibiting the plaintiff from recovering any monetary compensation as a result of the defendant's delays to the project.  The project was scheduled to finish on July 1, 2007, but was not completed until March 21, 2008 - 256 days beyond its scheduled completion date. As a result of the delays, the plaintiff suffered market-driven material and labor cost increases. The plaintiff adjusted its unit prices for increased costs arising from work performed after July 1, 2007, and invoiced the defendant for these increased costs.  When the defendant refused to pay, citing the "no damages for delay" clause, the plaintiff sub-subcontractor sued the subcontractor and the project's payment bond sureties. The trial court ruled in favor of the defendant subcontractor, finding that the "no damages for delay" clause trumped the "equitable adjustment" clause, and the plaintiff appealed.

The North Carolina Court of Appeals reversed the trial court and ruled in favor of the plaintiff, finding that the parties' contract allocated two distinct risks. The "no damages for delay" clause allocated to the plaintiff the risk with respect to responsibility for extended general conditions expenses arising from delay, while the "equitable adjustment" clause allocated to the defendant the risk of increased material and labor costs arising from unforeseen circumstances. Therefore, the "no damages for delay" clause did not bar recovery for market-driven cost increases associated with material and labor costs, incurred after the scheduled completion date.

The court found that the plaintiff could also recover against the sureties as a third-party beneficiary of the payment bond executed by the general contractor.  The court held that the plaintiff was clearly an intended beneficiary of the general contractor's payment bond, given that it was designed for the protection of "all persons supplying labor and materials" to the project.  Therefore, the plaintiff could recover against the sureties for the subcontractor's non-payment.

While "no damages for delay" clauses will continue to waive any claims for extended general conditions, according to the North Carolina Court of Appeals, claims for price increases in the contract due to delay will be preserved in contracts also containing an "equitable adjustment" clause.

 
Nevada's Highest Court Upholds Award Against Electrical Subcontractor That Reneged On Pre-Bid Price Quote. PDF Print

August 8, 2011 - This July, the Nevada Supreme Court ruled that a contractor was entitled to rely on a subcontractor's withdrawn bid under the doctrine of promissory estoppel.

Read more...
 
<< Start < Prev 1 2 Next > End >>

Page 1 of 2

News

NORTH CAROLINA COURT RULES THAT “NO DAMAGES FOR DELAY” CLAUSE DOES NOT TRUMP “EQUITABLE ADJUSTMENT” CLAUSE FOR COST ESCALATION CLAIMS.

January 25, 2012 - In Southern Seeding Serv., Inc. v. W.C. English, Inc., 2011 WL 6039951 (N.C. App. Dec. 6, 2011), the North Carolina Court of Appeals found that a ...

More

ROBERT J. DIETZ HAS BEEN MADE OF COUNSEL TO BRIGLIAMCLAUGHLIN.

January 6, 2012 - BrigliaMcLaughlin, PLLC, a nationally recognized construction law firm based in Tysons Corner, Virginia, is pleased to announce that Robert J. Dietz has been made Of Counsel ...

More

SHANNON J. BRIGLIA NAMED 2012 D.C. SUPER LAWYER.

December 13, 2011 - Shannon J. Briglia has again been named a Washington, D.C. Super Lawyer for her work in construction and surety law. Super Lawyers is a rating service of ...

More
©2008 BrigliaMcLaughlin, PLLC - View Disclaimer
Law Firm Web Design by The Modern Firm